European public procurement and grants data from official registers · Data as of 18 November 2026; updated daily.

Market report

Water and sewer pipeline tenders in Portugal — market report, April 2025

Water and sewer pipeline tenders in Portugal in April 2025: 62 tenders published (-39% month on month, +9% year on year), estimated at €23,639,413 in total, and 41 contracts awarded (-43% month on month, -5% year on year), worth €12,217,825 (contract value). Buyers with the most tenders: Águas do Norte, S. A. (14), Vimágua - Empresa de Água e Saneamento de Guimarães e Vizela, EIM, SA (5) and Serviços Municipalizados de Água e Saneamento de Vila Franca de Xira (4); most contracts won: DIZconstrução Lda (4), Vaz & Barbosa, Lda (3) and Amydra Construções Lda. (3). On average 3.0 bids per contract; 42% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
62
Contracts awarded
41
Contract value contract
€12,217,825
Bids per contract
3.0
Tenders published per month
050100150Apr 24: 57Apr 24: 57Apr 24May 24: 70May 24: 70May 24Jun 24: 84Jun 24: 84Jun 24Jul 24: 80Jul 24: 80Jul 24Aug 24: 33Aug 24: 33Aug 24Sep 24: 39Sep 24: 39Sep 24Oct 24: 103Oct 24: 103Oct 24Nov 24: 81Nov 24: 81Nov 24Dec 24: 74Dec 24: 74Dec 24Jan 25: 86Jan 25: 86Jan 25Feb 25: 64Feb 25: 64Feb 25Mar 25: 101Mar 25: 101Mar 25Apr 25: 62Apr 25: 6262Apr 25
Contracts awarded per month
050100Apr 24: 43Apr 24: 43Apr 24May 24: 56May 24: 56May 24Jun 24: 74Jun 24: 74Jun 24Jul 24: 49Jul 24: 49Jul 24Aug 24: 22Aug 24: 22Aug 24Sep 24: 41Sep 24: 41Sep 24Oct 24: 83Oct 24: 83Oct 24Nov 24: 61Nov 24: 61Nov 24Dec 24: 66Dec 24: 66Dec 24Jan 25: 68Jan 25: 68Jan 25Feb 25: 34Feb 25: 34Feb 25Mar 25: 72Mar 25: 72Mar 25Apr 25: 41Apr 25: 4141Apr 25

The highlighted bar is April 2025. Hover a bar for its figure; the table below has every value.

FigureApril 2025March 2025ChangeApril 2024Change
Tenders published62101-39%57+9%
Estimated value€23,639,413€48,788,722-52%€7,173,686+230%
Buyers2924+21%17+71%
Contracts awarded4172-43%43-5%
Contract value (contract)€12,217,825€6,020,919+103%€3,638,220+236%
Winners25250%23+9%
Bids per contract3.03.0—3.4—
Single-bid contracts42%36%—31%—

Buyers with the most tenders

Companies with the most contracts

Procedures

  • not stated 36
  • Open procedure 25
  • Restricted procedure 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Water and sewer pipelines

Questions and answers

How many water and sewer pipeline tenders were published in Portugal in April 2025?
62 (by 29 buyers); for comparison, March 2025: 101, April 2024: 57.
Who won the most water and sewer pipeline tenders in Portugal in April 2025?
By number of contracts: DIZconstrução Lda (4), Vaz & Barbosa, Lda (3), Amydra Construções Lda. (3), Questão d'Área, Lda (2) and Joaquim Rodrigues da Silva & Filhos, Lda. (2); 25 companies won contracts in all.
Which buyers published the most water and sewer pipeline tenders in April 2025?
Águas do Norte, S. A. (14), Vimágua - Empresa de Água e Saneamento de Guimarães e Vizela, EIM, SA (5), Serviços Municipalizados de Água e Saneamento de Vila Franca de Xira (4), AGERE- Empresa de Águas Efluentes e Resíduos de Braga, EM (3) and Serviços Municipalizados de Águas e Saneamento de Mafra - SMAS de Mafra (3).
How competitive were water and sewer pipeline tenders in Portugal in April 2025?
On average 3.0 bids per contract (24 contracts with a known number of bids); 42% of contracts had a single bid.
What were the contracts worth in April 2025?
€12,217,825 (contract value, 41 contracts); median about €97,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.