Road maintenance tenders in Portugal — market report, March 2025

Road maintenance tenders in Portugal in March 2025: 106 tenders published (+23% month on month, +25% year on year), estimated at €44,850,416 in total, and 106 contracts awarded (+130% month on month, +47% year on year), worth €2,999,998 (awarded value). Buyers with the most tenders: Infraestruturas de Portugal, S. A. (10), Município da Póvoa de Lanhoso (6) and Gestão e Obras do Porto, E. M. (5); most contracts won: CME - Construção e Manutenção Electromecânica, S.A. (4), SEGMENTOPROVÁVEL- Serviços e Manutenção, Lda (3) and AFAVIAS - Engenharia e Construções, S.A. (3). On average 5.7 bids per contract; 23% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
106
Contracts awarded
106
Contract value awarded
€2,999,998
Bids per contract
5.7
Tenders published per month
050100150Mar 24: 85Mar 24: 85Mar 24Apr 24: 112Apr 24: 112Apr 24May 24: 97May 24: 97May 24Jun 24: 99Jun 24: 99Jun 24Jul 24: 125Jul 24: 125Jul 24Aug 24: 87Aug 24: 87Aug 24Sep 24: 98Sep 24: 98Sep 24Oct 24: 103Oct 24: 103Oct 24Nov 24: 86Nov 24: 86Nov 24Dec 24: 72Dec 24: 72Dec 24Jan 25: 115Jan 25: 115Jan 25Feb 25: 86Feb 25: 86Feb 25Mar 25: 106Mar 25: 106106Mar 25
Contracts awarded per month
050100150Mar 24: 72Mar 24: 72Mar 24Apr 24: 84Apr 24: 84Apr 24May 24: 81May 24: 81May 24Jun 24: 73Jun 24: 73Jun 24Jul 24: 71Jul 24: 71Jul 24Aug 24: 54Aug 24: 54Aug 24Sep 24: 90Sep 24: 90Sep 24Oct 24: 73Oct 24: 73Oct 24Nov 24: 47Nov 24: 47Nov 24Dec 24: 51Dec 24: 51Dec 24Jan 25: 49Jan 25: 49Jan 25Feb 25: 46Feb 25: 46Feb 25Mar 25: 106Mar 25: 106106Mar 25

The highlighted bar is March 2025. Hover a bar for its figure; the table below has every value.

FigureMarch 2025February 2025ChangeMarch 2024Change
Tenders published10686+23%85+25%
Estimated value€44,850,416€22,209,328+102%€88,172,729-49%
Buyers60600%43+40%
Contracts awarded10646+130%72+47%
Contract value (awarded)€2,999,998€612,590+390%€7,501,907-60%
Winners7536+108%44+70%
Bids per contract5.72.7—6.8—
Single-bid contracts23%65%—22%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Centro (PT) 2

Procedures

  • not stated 57
  • Open procedure 48
  • Restricted procedure 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Road repairs and maintenance

Questions and answers

How many road maintenance tenders were published in Portugal in March 2025?
106 (by 60 buyers); for comparison, February 2025: 86, March 2024: 85.
Who won the most road maintenance tenders in Portugal in March 2025?
By number of contracts: CME - Construção e Manutenção Electromecânica, S.A. (4), SEGMENTOPROVÁVEL- Serviços e Manutenção, Lda (3), AFAVIAS - Engenharia e Construções, S.A. (3), MURBAN - Mobiliário Urbano e Serviços, Lda. (2) and Volumes e Fragmentos - Serviços, Unipessoal, Lda. (2); 75 companies won contracts in all.
Which buyers published the most road maintenance tenders in March 2025?
Infraestruturas de Portugal, S. A. (10), Município da Póvoa de Lanhoso (6), Gestão e Obras do Porto, E. M. (5), Município de Alfândega da Fé (5) and Município de Aljezur (4).
How competitive were road maintenance tenders in Portugal in March 2025?
On average 5.7 bids per contract (71 contracts with a known number of bids); 23% of contracts had a single bid.
What were the contracts worth in March 2025?
€2,999,998 (awarded value, 106 contracts); median about €140,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.