Water main tenders in Poland in April 2025: 109 tenders published (+17% month on month, 0% year on year), estimated at €21,229,805 in total, and 63 contracts awarded (+47% month on month, +13% year on year), worth €25,834,577 (awarded value). Buyers with the most tenders: Veoila Energia Poznań S.A. (5), Gmina Magnuszew (2) and Brzeskie Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. (2); most contracts won: KADA – BIS Spółka z o. o (8), Budynk Sp. z o.o. (3) and Blanca Plus Sp. z o.o. (3). On average 7.3 bids per contract; 3% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
109
Contracts awarded
63
Contract value awarded
€25,834,577
Bids per contract
7.3
Tenders published per month
050100150Apr 24: 109Apr 24: 109Apr 24May 24: 115May 24: 115May 24Jun 24: 136Jun 24: 136Jun 24Jul 24: 130Jul 24: 130Jul 24Aug 24: 60Aug 24: 60Aug 24Sep 24: 80Sep 24: 80Sep 24Oct 24: 96Oct 24: 96Oct 24Nov 24: 60Nov 24: 60Nov 24Dec 24: 51Dec 24: 51Dec 24Jan 25: 66Jan 25: 66Jan 25Feb 25: 82Feb 25: 82Feb 25Mar 25: 93Mar 25: 93Mar 25Apr 25: 109Apr 25: 109109Apr 25
Contracts awarded per month
050100150Apr 24: 56Apr 24: 56Apr 24May 24: 74May 24: 74May 24Jun 24: 59Jun 24: 59Jun 24Jul 24: 81Jul 24: 81Jul 24Aug 24: 106Aug 24: 106Aug 24Sep 24: 101Sep 24: 101Sep 24Oct 24: 71Oct 24: 71Oct 24Nov 24: 64Nov 24: 64Nov 24Dec 24: 33Dec 24: 33Dec 24Jan 25: 45Jan 25: 45Jan 25Feb 25: 26Feb 25: 26Feb 25Mar 25: 43Mar 25: 43Mar 25Apr 25: 63Apr 25: 6363Apr 25

The highlighted bar is April 2025. Hover a bar for its figure; the table below has every value.

FigureApril 2025March 2025ChangeApril 2024Change
Tenders published10993+17%1090%
Estimated value€21,229,805€29,099,808-27%€11,288,625+88%
Buyers8979+13%100-11%
Contracts awarded6343+47%56+13%
Contract value (awarded)€25,834,577€11,708,786+121%€49,076,535-47%
Winners2521+19%26-4%
Bids per contract7.38.9—5.6—
Single-bid contracts3%6%—3%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Mazowiecki regionalny 17
  • Małopolskie 10
  • Dolnośląskie 8
  • Lubelskie 8
  • Pomorskie 6

Procedures

  • Simplified procedure 77
  • Other procedure 19
  • not stated 5
  • Direct award 5
  • Open procedure 3

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Water mains and water supply networks

Questions and answers

How many water main tenders were published in Poland in April 2025?
109 (by 89 buyers); for comparison, March 2025: 93, April 2024: 109.
Who won the most water main tenders in Poland in April 2025?
By number of contracts: KADA – BIS Spółka z o. o (8), Budynk Sp. z o.o. (3), Blanca Plus Sp. z o.o. (3), KM INWESTYCJE sp. z o.o. (3) and Monomer Sp. z o.o. (3); 25 companies won contracts in all.
Which buyers published the most water main tenders in April 2025?
Veoila Energia Poznań S.A. (5), Gmina Magnuszew (2), Brzeskie Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. (2), Centralny Ośrodek Sportu z siedzibą w Warszawie, (00-449), ul. Łazienkowska 6A, Ośrodek Przygotowań Olimpijskich we Władysławowie (84-120) ul. Żeromskiego 52 (2) and Gminny Zakład Komunalny (2).
How competitive were water main tenders in Poland in April 2025?
On average 7.3 bids per contract (29 contracts with a known number of bids); 3% of contracts had a single bid.
What were the contracts worth in April 2025?
€25,834,577 (awarded value, 63 contracts); median about €290,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.