Market report
Street lighting installation tenders in Poland: monthly market reports
Street lighting installation tenders in Poland in October 2026: 117 tenders published (-44% month on month, -38% year on year), estimated at €4,855,576 in total, and 80 contracts awarded (-38% month on month, -61% year on year), worth €17,368,505 (awarded value). Buyers with the most tenders: Gmina Haczów (2), Gmina Ostrów Mazowiecka (2) and Zarząd Dróg i Zieleni w Pile (2); most contracts won: Elektroinstal Rogulscy S.C. (6), SEM Zakład Elektrotechniczny Jakub Maćkowiak, Stefan Mackowiak Sp.j (6) and 3D Sp. z o.o, (3). GranTender publishes a market report on street lighting installation tenders in Poland every month; 22 so far.
Read the latest report: October 2026
The highlighted bar is October 2026. Hover a bar for its figure; the table below has every value.
Every month
| Month | Tenders published | Buyers | Contracts awarded | Winners | Bids per contract |
|---|---|---|---|---|---|
| October 2026 | 117 | 89 | 80 | 50 | 3.5 |
| September 2026 | 209 | 158 | 130 | 76 | 4.0 |
| August 2026 | 198 | 158 | 150 | 70 | 4.0 |
| July 2026 | 261 | 190 | 149 | 84 | 4.2 |
| June 2026 | 219 | 173 | 188 | 90 | 4.6 |
| May 2026 | 212 | 168 | 168 | 84 | 4.9 |
| April 2026 | 235 | 186 | 176 | 76 | 5.7 |
| March 2026 | 255 | 167 | 129 | 60 | 6.1 |
| February 2026 | 142 | 107 | 45 | 28 | 6.0 |
| January 2026 | 98 | 70 | 93 | 36 | 4.5 |
| December 2025 | 92 | 63 | 123 | 53 | 4.6 |
| November 2025 | 117 | 87 | 149 | 54 | 4.7 |
| October 2025 | 190 | 148 | 206 | 73 | 4.2 |
| September 2025 | 205 | 156 | 218 | 70 | 5.0 |
| August 2025 | 177 | 136 | 254 | 87 | 4.7 |
| July 2025 | 233 | 183 | 292 | 86 | 5.3 |
| June 2025 | 181 | 138 | 191 | 64 | 6.6 |
| May 2025 | 194 | 143 | 205 | 69 | 6.3 |
| April 2025 | 182 | 134 | 197 | 70 | 6.8 |
| March 2025 | 196 | 146 | 164 | 51 | 7.2 |
| February 2025 | 149 | 106 | 91 | 39 | 6.6 |
| January 2025 | 171 | 119 | 119 | 47 | 5.7 |
| December 2024 | 118 | 81 | 253 | 68 | 4.6 |
| November 2024 | 137 | 106 | 346 | 85 | 4.4 |
| October 2024 | 205 | 149 | 450 | 110 | 4.6 |
| September 2024 | 628 | 537 | 346 | 92 | 4.3 |
| August 2024 | 328 | 275 | 255 | 86 | 4.3 |
| July 2024 | 295 | 236 | 285 | 104 | 5.1 |
| June 2024 | 299 | 249 | 254 | 67 | 5.3 |
| May 2024 | 230 | 169 | 183 | 61 | 5.5 |
| April 2024 | 272 | 198 | 227 | 73 | 5.1 |
| March 2024 | 318 | 222 | 198 | 71 | 5.3 |
| February 2024 | 352 | 228 | 78 | 32 | 6.7 |
Market reports
Other topics of Building construction and materials
Questions and answers
- How many street lighting installation tenders were published in Poland in October 2026?
- 117 (by 89 buyers); for comparison, September 2026: 209, October 2025: 190.
- Who won the most street lighting installation tenders in Poland in October 2026?
- By number of contracts: Elektroinstal Rogulscy S.C. (6), SEM Zakład Elektrotechniczny Jakub Maćkowiak, Stefan Mackowiak Sp.j (6), 3D Sp. z o.o, (3), WERTUS Sp. z o.o., (3) and ELMAT s.c. A.J. Kudzia (2); 50 companies won contracts in all.
- Which buyers published the most street lighting installation tenders in October 2026?
- Gmina Haczów (2), Gmina Ostrów Mazowiecka (2), Zarząd Dróg i Zieleni w Pile (2), Miasto Ząbki (2) and Gmina Żabia Wola (2).
- How competitive were street lighting installation tenders in Poland in October 2026?
- On average 3.5 bids per contract (74 contracts with a known number of bids); 8% of contracts had a single bid.
- What were the contracts worth in October 2026?
- €17,368,505 (awarded value, 80 contracts); median about €55,000.
How the report is made
Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 8 November 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.