Solar PV tenders in Poland in December 2025: 154 tenders published (-2% month on month, +35% year on year), estimated at €18,031,126 in total, and 115 contracts awarded (+14% month on month, +58% year on year), worth €28,960,424 (awarded value). Buyers with the most tenders: ALEKSANDRIA S.C. Karolina Hadam, Daniel Hadam (3), ZPUE SA (3) and ECO FIX sp. z o. o. (3); most contracts won: Flexipower Group sp. z o.o. sp.k. (8), EKO-ON Sp. z o.o. (7) and Sunector Sp. z o.o. (6). On average 6.4 bids per contract; 21% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
154
Contracts awarded
115
Contract value awarded
€28,960,424
Bids per contract
6.4
Tenders published per month
0100200300Dec 24: 114Dec 24: 114Dec 24Jan 25: 139Jan 25: 139Jan 25Feb 25: 167Feb 25: 167Feb 25Mar 25: 178Mar 25: 178Mar 25Apr 25: 228Apr 25: 228Apr 25May 25: 179May 25: 179May 25Jun 25: 199Jun 25: 199Jun 25Jul 25: 221Jul 25: 221Jul 25Aug 25: 157Aug 25: 157Aug 25Sep 25: 175Sep 25: 175Sep 25Oct 25: 204Oct 25: 204Oct 25Nov 25: 157Nov 25: 157Nov 25Dec 25: 154Dec 25: 154154Dec 25
Contracts awarded per month
050100150200Dec 24: 73Dec 24: 73Dec 24Jan 25: 50Jan 25: 50Jan 25Feb 25: 21Feb 25: 21Feb 25Mar 25: 55Mar 25: 55Mar 25Apr 25: 57Apr 25: 57Apr 25May 25: 68May 25: 68May 25Jun 25: 71Jun 25: 71Jun 25Jul 25: 128Jul 25: 128Jul 25Aug 25: 102Aug 25: 102Aug 25Sep 25: 100Sep 25: 100Sep 25Oct 25: 157Oct 25: 157Oct 25Nov 25: 101Nov 25: 101Nov 25Dec 25: 115Dec 25: 115115Dec 25

The highlighted bar is December 2025. Hover a bar for its figure; the table below has every value.

FigureDecember 2025November 2025ChangeDecember 2024Change
Tenders published154157-2%114+35%
Estimated value€18,031,126€11,183,528+61%€4,671,933+286%
Buyers9697-1%69+39%
Contracts awarded115101+14%73+58%
Contract value (awarded)€28,960,424€22,474,846+29%€8,682,301+234%
Winners4642+10%27+70%
Bids per contract6.46.3—6.3—
Single-bid contracts21%9%—13%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Śląskie 19
  • Wielkopolskie 6
  • Łódzkie 6
  • Małopolskie 4
  • Dolnośląskie 2

Procedures

  • Other procedure 103
  • Simplified procedure 29
  • Open procedure 18
  • Direct award 4

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Solar PV and solar installations

Questions and answers

How many solar PV tenders were published in Poland in December 2025?
154 (by 96 buyers); for comparison, November 2025: 157, December 2024: 114.
Who won the most solar PV tenders in Poland in December 2025?
By number of contracts: Flexipower Group sp. z o.o. sp.k. (8), EKO-ON Sp. z o.o. (7), Sunector Sp. z o.o. (6), Arinea sp. z o.o. (6) and Let'S Go Green spółka z ograniczoną odpowiedzialnością (5); 46 companies won contracts in all.
Which buyers published the most solar PV tenders in December 2025?
ALEKSANDRIA S.C. Karolina Hadam, Daniel Hadam (3), ZPUE SA (3), ECO FIX sp. z o. o. (3), DomkiNadBialka.pl Julian Babula; Kantor Wymiany Walut Julian, Dorota i Bożena Babula Spółka Cywilna; TANIA ODZIEŻ Dorota i Julian Babula Spółka Cywilna; Biuro Księgowo-Doradczo-Szkoleniowe Julian i Bożena Babula (3) and Z4L Sp. z o.o. (2).
How competitive were solar PV tenders in Poland in December 2025?
On average 6.4 bids per contract (38 contracts with a known number of bids); 21% of contracts had a single bid.
What were the contracts worth in December 2025?
€28,960,424 (awarded value, 115 contracts); median about €52,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.