European public procurement and grants data from official registers · Data as of 17 November 2026; updated daily.

Market report

Switchgear tenders in Italy — market report, January 2026

Switchgear tenders in Italy in January 2026: 114 tenders published (-53% month on month, -42% year on year), estimated at €12,607,589 in total, and 45 contracts awarded (-52% month on month, -30% year on year), worth €5,900,232 (awarded value). Buyers with the most tenders: E-DISTRIBUZIONE SPA (8), Set Distribuzione SPA (4) and Terna Rete Italia S.P.A (4); most contracts won: Elco Ingross S.R.L. Unipersonale (3), Gruppo Giovannini S.R.L. (2) and IN.EL.CO. S.R.L. (1). On average 2.9 bids per contract; 50% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
114
Contracts awarded
45
Contract value awarded
€5,900,232
Bids per contract
2.9
Tenders published per month
0100200300Jan 25: 195Jan 25: 195Jan 25Feb 25: 170Feb 25: 170Feb 25Mar 25: 191Mar 25: 191Mar 25Apr 25: 243Apr 25: 243Apr 25May 25: 196May 25: 196May 25Jun 25: 215Jun 25: 215Jun 25Jul 25: 288Jul 25: 288Jul 25Aug 25: 96Aug 25: 96Aug 25Sep 25: 161Sep 25: 161Sep 25Oct 25: 237Oct 25: 237Oct 25Nov 25: 196Nov 25: 196Nov 25Dec 25: 244Dec 25: 244Dec 25Jan 26: 114Jan 26: 114114Jan 26
Contracts awarded per month
050100150Jan 25: 64Jan 25: 64Jan 25Feb 25: 64Feb 25: 64Feb 25Mar 25: 67Mar 25: 67Mar 25Apr 25: 87Apr 25: 87Apr 25May 25: 107May 25: 107May 25Jun 25: 97Jun 25: 97Jun 25Jul 25: 95Jul 25: 95Jul 25Aug 25: 39Aug 25: 39Aug 25Sep 25: 72Sep 25: 72Sep 25Oct 25: 106Oct 25: 106Oct 25Nov 25: 86Nov 25: 86Nov 25Dec 25: 94Dec 25: 94Dec 25Jan 26: 45Jan 26: 4545Jan 26

The highlighted bar is January 2026. Hover a bar for its figure; the table below has every value.

FigureJanuary 2026December 2025ChangeJanuary 2025Change
Tenders published114244-53%195-42%
Estimated value€12,607,589€363,644,184-97%€23,320,018-46%
Buyers51112-54%81-37%
Contracts awarded4594-52%64-30%
Contract value (awarded)€5,900,232€29,057,396-80%€15,853,814-63%
Winners3677-53%50-28%
Bids per contract2.92.6—1.3—
Single-bid contracts50%45%—83%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Piemonte 5
  • Lazio 5
  • Lombardia 4
  • Veneto 4
  • Sicilia 3

Procedures

  • Direct award 81
  • Negotiated procedure without prior publication 14
  • Other procedure 7
  • not stated 5
  • Negotiated procedure 5
  • Open procedure 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Switchgear and distribution boards

Questions and answers

How many switchgear tenders were published in Italy in January 2026?
114 (by 51 buyers); for comparison, December 2025: 244, January 2025: 195.
Who won the most switchgear tenders in Italy in January 2026?
By number of contracts: Elco Ingross S.R.L. Unipersonale (3), Gruppo Giovannini S.R.L. (2), IN.EL.CO. S.R.L. (1), ALIFAX S.R.L. (1) and En-Co di Steindl Robert & C. SNC (1); 36 companies won contracts in all.
Which buyers published the most switchgear tenders in January 2026?
E-DISTRIBUZIONE SPA (8), Set Distribuzione SPA (4), Terna Rete Italia S.P.A (4), Consorzio di Bonifica Brenta (4) and Societa Risorse Idriche Calabresi (4).
How competitive were switchgear tenders in Italy in January 2026?
On average 2.9 bids per contract (10 contracts with a known number of bids); 50% of contracts had a single bid.
What were the contracts worth in January 2026?
€5,900,232 (awarded value, 45 contracts); median about €17,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.