European public procurement and grants data from official registers · Data as of 17 November 2026; updated daily.

Market report

Road construction tenders in Italy — market report, July 2025

Road construction tenders in Italy in July 2025: 624 tenders published (-3% month on month, +7% year on year), estimated at €220,853,318 in total, and 253 contracts awarded (-12% month on month, -7% year on year), worth €821,088,098 (awarded value). Buyers with the most tenders: Regione Autonoma Valle d'Aosta (19), ANAS SPA (15) and Amministrazione Provinciale Forli'-Cesena (14); most contracts won: Canovi Costruzioni SRL (3), Civelli Costruzioni S.R.L. (3) and RM Appalti S.P.A. (2). On average 13.8 bids per contract; 8% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
624
Contracts awarded
253
Contract value awarded
€821,088,098
Bids per contract
13.8
Tenders published per month
05001KJul 24: 585Jul 24: 585Jul 24Aug 24: 391Aug 24: 391Aug 24Sep 24: 575Sep 24: 575Sep 24Oct 24: 630Oct 24: 630Oct 24Nov 24: 566Nov 24: 566Nov 24Dec 24: 894Dec 24: 894Dec 24Jan 25: 448Jan 25: 448Jan 25Feb 25: 394Feb 25: 394Feb 25Mar 25: 455Mar 25: 455Mar 25Apr 25: 470Apr 25: 470Apr 25May 25: 526May 25: 526May 25Jun 25: 646Jun 25: 646Jun 25Jul 25: 624Jul 25: 624624Jul 25
Contracts awarded per month
0100200300400Jul 24: 273Jul 24: 273Jul 24Aug 24: 184Aug 24: 184Aug 24Sep 24: 252Sep 24: 252Sep 24Oct 24: 266Oct 24: 266Oct 24Nov 24: 208Nov 24: 208Nov 24Dec 24: 393Dec 24: 393Dec 24Jan 25: 123Jan 25: 123Jan 25Feb 25: 198Feb 25: 198Feb 25Mar 25: 189Mar 25: 189Mar 25Apr 25: 211Apr 25: 211Apr 25May 25: 301May 25: 301May 25Jun 25: 289Jun 25: 289Jun 25Jul 25: 253Jul 25: 253253Jul 25

The highlighted bar is July 2025. Hover a bar for its figure; the table below has every value.

FigureJuly 2025June 2025ChangeJuly 2024Change
Tenders published624646-3%585+7%
Estimated value€220,853,318€305,606,234-28%€627,703,448-65%
Buyers3113100%284+10%
Contracts awarded253289-12%273-7%
Contract value (awarded)€821,088,098€123,372,430+566%€173,396,766+374%
Winners228236-3%237-4%
Bids per contract13.815.0—4.9—
Single-bid contracts8%8%—12%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Lombardia 43
  • Emilia-Romagna 27
  • Veneto 25
  • Piemonte 19
  • Sicilia 19

Procedures

  • Direct award 406
  • Negotiated procedure without prior publication 109
  • Open procedure 44
  • Other procedure 40
  • Negotiated procedure 12
  • not stated 9

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Road construction

Questions and answers

How many road construction tenders were published in Italy in July 2025?
624 (by 311 buyers); for comparison, June 2025: 646, July 2024: 585.
Who won the most road construction tenders in Italy in July 2025?
By number of contracts: Canovi Costruzioni SRL (3), Civelli Costruzioni S.R.L. (3), RM Appalti S.P.A. (2), Consorzio Stabile 3 Emme Difesa Ambiente e Territorio Soc. Cons. a R.L. (2) and F e a S.R.L. (2); 228 companies won contracts in all.
Which buyers published the most road construction tenders in July 2025?
Regione Autonoma Valle d'Aosta (19), ANAS SPA (15), Amministrazione Provinciale Forli'-Cesena (14), Provincia di Fermo (12) and Comune di Polinago (10).
How competitive were road construction tenders in Italy in July 2025?
On average 13.8 bids per contract (76 contracts with a known number of bids); 8% of contracts had a single bid.
What were the contracts worth in July 2025?
€821,088,098 (awarded value, 253 contracts); median about €110,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.