European public procurement and grants data from official registers · Data as of 17 November 2026; updated daily.

Market report

Meter reading tenders in Italy — market report, December 2025

Meter reading tenders in Italy in December 2025: 77 tenders published (+79% month on month, +45% year on year), estimated at €6,594,830 in total, and 37 contracts awarded (+164% month on month, +28% year on year), worth €2,851,600 (awarded value). Buyers with the most tenders: Comune di Sarezzo (6), Ap Reti Gas S.P.A. a Socio Unico (5) and Comune di Sella Giudicarie (4); most contracts won: IMPLANET.IT S.R.L.S. (2), INOVA S.R.L. (2) and M.B.S. Group Societa' Consortile a Responsabilita' Limitata (2). On average 3.6 bids per contract; 0% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
77
Contracts awarded
37
Contract value awarded
€2,851,600
Bids per contract
3.6
Tenders published per month
020406080Dec 24: 53Dec 24: 53Dec 24Jan 25: 47Jan 25: 47Jan 25Feb 25: 38Feb 25: 38Feb 25Mar 25: 31Mar 25: 31Mar 25Apr 25: 19Apr 25: 19Apr 25May 25: 39May 25: 39May 25Jun 25: 51Jun 25: 51Jun 25Jul 25: 43Jul 25: 43Jul 25Aug 25: 36Aug 25: 36Aug 25Sep 25: 25Sep 25: 25Sep 25Oct 25: 58Oct 25: 58Oct 25Nov 25: 43Nov 25: 43Nov 25Dec 25: 77Dec 25: 7777Dec 25
Contracts awarded per month
010203040Dec 24: 29Dec 24: 29Dec 24Jan 25: 30Jan 25: 30Jan 25Feb 25: 13Feb 25: 13Feb 25Mar 25: 13Mar 25: 13Mar 25Apr 25: 7Apr 25: 7Apr 25May 25: 15May 25: 15May 25Jun 25: 33Jun 25: 33Jun 25Jul 25: 32Jul 25: 32Jul 25Aug 25: 12Aug 25: 12Aug 25Sep 25: 26Sep 25: 26Sep 25Oct 25: 23Oct 25: 23Oct 25Nov 25: 14Nov 25: 14Nov 25Dec 25: 37Dec 25: 3737Dec 25

The highlighted bar is December 2025. Hover a bar for its figure; the table below has every value.

FigureDecember 2025November 2025ChangeDecember 2024Change
Tenders published7743+79%53+45%
Estimated value€6,594,830€12,482,914-47%€4,489,149+47%
Buyers3221+52%24+33%
Contracts awarded3714+164%29+28%
Contract value (awarded)€2,851,600€1,742,318+64%€7,449,900-62%
Winners3212+167%18+78%
Bids per contract3.6————
Single-bid contracts0%————

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Lombardia 12
  • Veneto 7
  • Piemonte 6
  • Provincia Autonoma di Trento 3
  • Marche 3

Procedures

  • Direct award 64
  • Negotiated procedure without prior publication 9
  • Restricted procedure 2
  • not stated 1
  • Open procedure 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Meter reading services

Questions and answers

How many meter reading tenders were published in Italy in December 2025?
77 (by 32 buyers); for comparison, November 2025: 43, December 2024: 53.
Who won the most meter reading tenders in Italy in December 2025?
By number of contracts: IMPLANET.IT S.R.L.S. (2), INOVA S.R.L. (2), M.B.S. Group Societa' Consortile a Responsabilita' Limitata (2), Odoardo Zecca S.R.L. (1) and Coin Service S.P.A. (1); 32 companies won contracts in all.
Which buyers published the most meter reading tenders in December 2025?
Comune di Sarezzo (6), Ap Reti Gas S.P.A. a Socio Unico (5), Comune di Sella Giudicarie (4), Distribuzione Elettrica Adriatica S.P.A. (4) and AM+ S.P.A. (4).
How competitive were meter reading tenders in Italy in December 2025?
On average 3.6 bids per contract (5 contracts with a known number of bids); 0% of contracts had a single bid.
What were the contracts worth in December 2025?
€2,851,600 (awarded value, 37 contracts); median about €34,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.