European public procurement and grants data from official registers · Data as of 17 November 2026; updated daily.

Market report

School construction tenders in France — market report, June 2026

School construction tenders in France in June 2026: 387 tenders published (+18% month on month, -45% year on year), estimated at €14,573,521 in total, and 359 contracts awarded (+14% month on month, -51% year on year), worth €59,631,207 (awarded value). Buyers with the most tenders: Conseil départemental du Cantal (30), (18) and Mairie de Saint Georges de l'Oyapock (14); most contracts won: PROFLOREST 07 (4), GAMM (3) and Spl Arac Occitanie (3). On average 4.2 bids per contract; 11% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
387
Contracts awarded
359
Contract value awarded
€59,631,207
Bids per contract
4.2
Tenders published per month
0200400600800Jun 25: 703Jun 25: 703Jun 25Jul 25: 541Jul 25: 541Jul 25Aug 25: 186Aug 25: 186Aug 25Sep 25: 280Sep 25: 280Sep 25Oct 25: 398Oct 25: 398Oct 25Nov 25: 213Nov 25: 213Nov 25Dec 25: 311Dec 25: 311Dec 25Jan 26: 193Jan 26: 193Jan 26Feb 26: 242Feb 26: 242Feb 26Mar 26: 385Mar 26: 385Mar 26Apr 26: 218Apr 26: 218Apr 26May 26: 327May 26: 327May 26Jun 26: 387Jun 26: 387387Jun 26
Contracts awarded per month
0200400600800Jun 25: 738Jun 25: 738Jun 25Jul 25: 602Jul 25: 602Jul 25Aug 25: 174Aug 25: 174Aug 25Sep 25: 227Sep 25: 227Sep 25Oct 25: 421Oct 25: 421Oct 25Nov 25: 230Nov 25: 230Nov 25Dec 25: 322Dec 25: 322Dec 25Jan 26: 234Jan 26: 234Jan 26Feb 26: 274Feb 26: 274Feb 26Mar 26: 389Mar 26: 389Mar 26Apr 26: 231Apr 26: 231Apr 26May 26: 315May 26: 315May 26Jun 26: 359Jun 26: 359359Jun 26

The highlighted bar is June 2026. Hover a bar for its figure; the table below has every value.

FigureJune 2026May 2026ChangeJune 2025Change
Tenders published387327+18%703-45%
Estimated value€14,573,521€19,725,000-26%€91,414,067-84%
Buyers9872+36%163-40%
Contracts awarded359315+14%738-51%
Contract value (awarded)€59,631,207€33,037,366+80%€142,938,800-58%
Winners271184+47%525-48%
Bids per contract4.26.8—11.8—
Single-bid contracts11%7%—11%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Ile-de-France 3
  • Nouvelle-Aquitaine 2
  • Provence-Alpes-Côte d’Azur 2
  • Bourgogne-Franche-Comté 1
  • Pays de la Loire 1

Procedures

  • not stated 335
  • Open procedure 32
  • Simplified procedure 16
  • Competitive dialogue 2
  • Negotiated procedure 2

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: School construction

Questions and answers

How many school construction tenders were published in France in June 2026?
387 (by 98 buyers); for comparison, May 2026: 327, June 2025: 703.
Who won the most school construction tenders in France in June 2026?
By number of contracts: PROFLOREST 07 (4), GAMM (3), Spl Arac Occitanie (3), POLYTRAVAUX (3) and Durant Fils SASU (3); 271 companies won contracts in all.
Which buyers published the most school construction tenders in June 2026?
Conseil départemental du Cantal (30), (18), Mairie de Saint Georges de l'Oyapock (14), Commune de Ferrières-en-Bray (12) and Communaute de Communes Terre de Picardie (11).
How competitive were school construction tenders in France in June 2026?
On average 4.2 bids per contract (295 contracts with a known number of bids); 11% of contracts had a single bid.
What were the contracts worth in June 2026?
€59,631,207 (awarded value, 359 contracts); median about €490,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.