Earthworks tenders in France in November 2025: 667 tenders published (-17% month on month, +2% year on year), estimated at €863,630,510 in total, and 721 contracts awarded (-4% month on month, +3% year on year), worth €311,908,013 (awarded value). Buyers with the most tenders: Mairie de Wintzenheim (17), SEMAPA (13) and Mairie d'Orsay (8); most contracts won: AXIONE (6), EUROVIA (5) and Schneider et Cie (5). On average 5.3 bids per contract; 16% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
667
Contracts awarded
721
Contract value awarded
€311,908,013
Bids per contract
5.3
Tenders published per month
05001K1.5KNov 24: 653Nov 24: 653Nov 24Dec 24: 844Dec 24: 844Dec 24Jan 25: 776Jan 25: 776Jan 25Feb 25: 676Feb 25: 676Feb 25Mar 25: 824Mar 25: 824Mar 25Apr 25: 924Apr 25: 924Apr 25May 25: 833May 25: 833May 25Jun 25: 1,025Jun 25: 1,025Jun 25Jul 25: 1,096Jul 25: 1,096Jul 25Aug 25: 550Aug 25: 550Aug 25Sep 25: 825Sep 25: 825Sep 25Oct 25: 803Oct 25: 803Oct 25Nov 25: 667Nov 25: 667667Nov 25
Contracts awarded per month
05001K1.5KNov 24: 697Nov 24: 697Nov 24Dec 24: 1,095Dec 24: 1,095Dec 24Jan 25: 752Jan 25: 752Jan 25Feb 25: 589Feb 25: 589Feb 25Mar 25: 851Mar 25: 851Mar 25Apr 25: 932Apr 25: 932Apr 25May 25: 906May 25: 906May 25Jun 25: 1,067Jun 25: 1,067Jun 25Jul 25: 1,197Jul 25: 1,197Jul 25Aug 25: 567Aug 25: 567Aug 25Sep 25: 882Sep 25: 882Sep 25Oct 25: 753Oct 25: 753Oct 25Nov 25: 721Nov 25: 721721Nov 25

The highlighted bar is November 2025. Hover a bar for its figure; the table below has every value.

FigureNovember 2025October 2025ChangeNovember 2024Change
Tenders published667803-17%653+2%
Estimated value€863,630,510€1,075,569,244-20%€169,862,371+408%
Buyers370472-22%357+4%
Contracts awarded721753-4%697+3%
Contract value (awarded)€311,908,013€220,467,883+41%€209,664,393+49%
Winners471493-4%433+9%
Bids per contract5.35.0—5.9—
Single-bid contracts16%15%—13%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Ile-de-France 16
  • Provence-Alpes-Côte d’Azur 15
  • Hauts-de-France 12
  • Pays de la Loire 10
  • Nouvelle-Aquitaine 8

Procedures

  • not stated 457
  • Open procedure 193
  • Negotiated procedure 11
  • Other procedure 5
  • Negotiated procedure without prior publication 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Earthworks and site preparation

Questions and answers

How many earthworks tenders were published in France in November 2025?
667 (by 370 buyers); for comparison, October 2025: 803, November 2024: 653.
Who won the most earthworks tenders in France in November 2025?
By number of contracts: AXIONE (6), EUROVIA (5), Schneider et Cie (5), Le Noyer Vert (4) and Nge Routes (4); 471 companies won contracts in all.
Which buyers published the most earthworks tenders in November 2025?
Mairie de Wintzenheim (17), SEMAPA (13), Mairie d'Orsay (8), Ville d'Igny (8) and Métropole Aix Marseille Provence (7).
How competitive were earthworks tenders in France in November 2025?
On average 5.3 bids per contract (466 contracts with a known number of bids); 16% of contracts had a single bid.
What were the contracts worth in November 2025?
€311,908,013 (awarded value, 721 contracts); median about €330,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.