European public procurement and grants data from official registers · Data as of 17 November 2026; updated daily.

Market report

Solar PV installation tenders in Spain — market report, March 2025

Solar PV installation tenders in Spain in March 2025: 52 tenders published (-16% month on month, -42% year on year), estimated at €25,733,250 in total, and 114 contracts awarded (-1% month on month, -33% year on year), worth €6,018,249 (awarded value). Buyers with the most tenders: Diputació de Barcelona (4), Ajuntament de Lleida (3) and Ajuntament de Viladecans (3); most contracts won: Ecotelia Servicios Energéticos, S.L. (6), Electricitat Boquet SL (5) and ACSA OBRAS E INFRAESTRUCTURAS SA Unipersonal (3). On average 5.7 bids per contract; 54% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
52
Contracts awarded
114
Contract value awarded
€6,018,249
Bids per contract
5.7
Tenders published per month
050100150Mar 24: 90Mar 24: 90Mar 24Apr 24: 78Apr 24: 78Apr 24May 24: 100May 24: 100May 24Jun 24: 144Jun 24: 144Jun 24Jul 24: 111Jul 24: 111Jul 24Aug 24: 49Aug 24: 49Aug 24Sep 24: 99Sep 24: 99Sep 24Oct 24: 72Oct 24: 72Oct 24Nov 24: 86Nov 24: 86Nov 24Dec 24: 75Dec 24: 75Dec 24Jan 25: 63Jan 25: 63Jan 25Feb 25: 62Feb 25: 62Feb 25Mar 25: 52Mar 25: 5252Mar 25
Contracts awarded per month
050100150200Mar 24: 171Mar 24: 171Mar 24Apr 24: 156Apr 24: 156Apr 24May 24: 143May 24: 143May 24Jun 24: 199Jun 24: 199Jun 24Jul 24: 165Jul 24: 165Jul 24Aug 24: 99Aug 24: 99Aug 24Sep 24: 156Sep 24: 156Sep 24Oct 24: 134Oct 24: 134Oct 24Nov 24: 147Nov 24: 147Nov 24Dec 24: 163Dec 24: 163Dec 24Jan 25: 98Jan 25: 98Jan 25Feb 25: 115Feb 25: 115Feb 25Mar 25: 114Mar 25: 114114Mar 25

The highlighted bar is March 2025. Hover a bar for its figure; the table below has every value.

FigureMarch 2025February 2025ChangeMarch 2024Change
Tenders published5262-16%90-42%
Estimated value€25,733,250€6,489,917+297%€14,225,343+81%
Buyers4254-22%62-32%
Contracts awarded114115-1%171-33%
Contract value (awarded)€6,018,249€11,179,569-46%€8,044,603-25%
Winners92104-12%142-35%
Bids per contract5.74.3—6.0—
Single-bid contracts54%53%—51%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Cataluña 5
  • Andalucía 5
  • Extremadura 4
  • Castilla y León 3
  • Comunitat Valenciana 3

Procedures

  • not stated 19
  • Simplified procedure 16
  • Direct award 8
  • Open procedure 8
  • Negotiated procedure without prior publication 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Solar PV installation works

Questions and answers

How many solar PV installation tenders were published in Spain in March 2025?
52 (by 42 buyers); for comparison, February 2025: 62, March 2024: 90.
Who won the most solar PV installation tenders in Spain in March 2025?
By number of contracts: Ecotelia Servicios Energéticos, S.L. (6), Electricitat Boquet SL (5), ACSA OBRAS E INFRAESTRUCTURAS SA Unipersonal (3), Electricitat Boquet, SL (2) and Ingelec Rioja S.L. (2); 92 companies won contracts in all.
Which buyers published the most solar PV installation tenders in March 2025?
Diputació de Barcelona (4), Ajuntament de Lleida (3), Ajuntament de Viladecans (3), Dirección General del Consejo Insular de la Energía de Gran Canaria (2) and Consejería de Agua, Agricultura, Ganadería y Pesca de la Región de Murcia (2).
How competitive were solar PV installation tenders in Spain in March 2025?
On average 5.7 bids per contract (95 contracts with a known number of bids); 54% of contracts had a single bid.
What were the contracts worth in March 2025?
€6,018,249 (awarded value, 114 contracts); median about €13,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.