European public procurement and grants data from official registers · Data as of 17 November 2026; updated daily.

Market report

Generator tenders in Spain — market report, January 2026

Generator tenders in Spain in January 2026: 77 tenders published (-31% month on month, +18% year on year), estimated at €18,999,471 in total, and 76 contracts awarded (-38% month on month, 0% year on year), worth €1,404,078 (awarded value). Buyers with the most tenders: Corporació Catalana de Mitjans Audiovisuals, SA (8), Presidencia de la Diputación Provincial de Alicante (3) and Ajuntament del Morell (3); most contracts won: Kiloenergia Grups Elec i Ser (4), Enelmo, SL (4) and Morillo Energy Rent S.A.U. (3). On average 1.8 bids per contract; 67% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
77
Contracts awarded
76
Contract value awarded
€1,404,078
Bids per contract
1.8
Tenders published per month
050100150Jan 25: 65Jan 25: 65Jan 25Feb 25: 68Feb 25: 68Feb 25Mar 25: 70Mar 25: 70Mar 25Apr 25: 75Apr 25: 75Apr 25May 25: 105May 25: 105May 25Jun 25: 89Jun 25: 89Jun 25Jul 25: 141Jul 25: 141Jul 25Aug 25: 84Aug 25: 84Aug 25Sep 25: 87Sep 25: 87Sep 25Oct 25: 117Oct 25: 117Oct 25Nov 25: 113Nov 25: 113Nov 25Dec 25: 112Dec 25: 112Dec 25Jan 26: 77Jan 26: 7777Jan 26
Contracts awarded per month
050100150Jan 25: 76Jan 25: 76Jan 25Feb 25: 72Feb 25: 72Feb 25Mar 25: 96Mar 25: 96Mar 25Apr 25: 89Apr 25: 89Apr 25May 25: 135May 25: 135May 25Jun 25: 130Jun 25: 130Jun 25Jul 25: 143Jul 25: 143Jul 25Aug 25: 100Aug 25: 100Aug 25Sep 25: 122Sep 25: 122Sep 25Oct 25: 150Oct 25: 150Oct 25Nov 25: 118Nov 25: 118Nov 25Dec 25: 122Dec 25: 122Dec 25Jan 26: 76Jan 26: 7676Jan 26

The highlighted bar is January 2026. Hover a bar for its figure; the table below has every value.

FigureJanuary 2026December 2025ChangeJanuary 2025Change
Tenders published77112-31%65+18%
Estimated value€18,999,471€3,307,279+474%€873,664+2,075%
Buyers5987-32%56+5%
Contracts awarded76122-38%760%
Contract value (awarded)€1,404,078€3,861,153-64%€1,928,992-27%
Winners5899-41%62-6%
Bids per contract1.81.8—2.2—
Single-bid contracts67%59%—67%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Comunitat Valenciana 11
  • Canarias 7
  • Comunidad de Madrid 5
  • País Vasco 3
  • Castilla-La Mancha 3

Procedures

  • not stated 33
  • Direct award 27
  • Open procedure 7
  • Simplified procedure 5
  • Other procedure 3
  • Negotiated procedure without prior publication 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Power generators and gensets

Questions and answers

How many generator tenders were published in Spain in January 2026?
77 (by 59 buyers); for comparison, December 2025: 112, January 2025: 65.
Who won the most generator tenders in Spain in January 2026?
By number of contracts: Kiloenergia Grups Elec i Ser (4), Enelmo, SL (4), Morillo Energy Rent S.A.U. (3), Calvo bpa, S.L. (3) and Electrogrupo Generadores y Grúas Miralles, S.L. (3); 58 companies won contracts in all.
Which buyers published the most generator tenders in January 2026?
Corporació Catalana de Mitjans Audiovisuals, SA (8), Presidencia de la Diputación Provincial de Alicante (3), Ajuntament del Morell (3), Figueres de Serveis, SA (2) and Gerencia de Infraestructuras y Equipamientos de Cultura O.A (2).
How competitive were generator tenders in Spain in January 2026?
On average 1.8 bids per contract (43 contracts with a known number of bids); 67% of contracts had a single bid.
What were the contracts worth in January 2026?
€1,404,078 (awarded value, 76 contracts); median about €2,400.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.