Fasteners tenders in Spain — market report, June 2026

Fasteners tenders in Spain in June 2026: 87 tenders published (+24% month on month, +21% year on year), estimated at €1,307,108 in total, and 77 contracts awarded (-6% month on month, -20% year on year), worth €1,226,891 (awarded value). Buyers with the most tenders: Dirección General de Renfe Ingeniería y Mantenimiento Sociedad Mercantil Estatal, S.A. (30), Junta de Gobierno Local del Ayuntamiento de Alicante (11) and Universitat de Girona (8); most contracts won: METALCO S.A. (5), SUMICAT S.L. (4) and Wurth España.sa (4). On average 2.2 bids per contract; 39% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
87
Contracts awarded
77
Contract value awarded
€1,226,891
Bids per contract
2.2
Tenders published per month
050100Jun 25: 72Jun 25: 72Jun 25Jul 25: 78Jul 25: 78Jul 25Aug 25: 64Aug 25: 64Aug 25Sep 25: 73Sep 25: 73Sep 25Oct 25: 96Oct 25: 96Oct 25Nov 25: 77Nov 25: 77Nov 25Dec 25: 49Dec 25: 49Dec 25Jan 26: 64Jan 26: 64Jan 26Feb 26: 75Feb 26: 75Feb 26Mar 26: 56Mar 26: 56Mar 26Apr 26: 63Apr 26: 63Apr 26May 26: 70May 26: 70May 26Jun 26: 87Jun 26: 8787Jun 26
Contracts awarded per month
050100Jun 25: 96Jun 25: 96Jun 25Jul 25: 83Jul 25: 83Jul 25Aug 25: 58Aug 25: 58Aug 25Sep 25: 76Sep 25: 76Sep 25Oct 25: 91Oct 25: 91Oct 25Nov 25: 92Nov 25: 92Nov 25Dec 25: 69Dec 25: 69Dec 25Jan 26: 43Jan 26: 43Jan 26Feb 26: 90Feb 26: 90Feb 26Mar 26: 67Mar 26: 67Mar 26Apr 26: 45Apr 26: 45Apr 26May 26: 82May 26: 82May 26Jun 26: 77Jun 26: 7777Jun 26

The highlighted bar is June 2026. Hover a bar for its figure; the table below has every value.

FigureJune 2026May 2026ChangeJune 2025Change
Tenders published8770+24%72+21%
Estimated value€1,307,108€3,807,484-66%€3,489,861-63%
Buyers2633-21%21+24%
Contracts awarded7782-6%96-20%
Contract value (awarded)€1,226,891€932,177+32%€2,477,936-50%
Winners4858-17%64-25%
Bids per contract2.23.0—4.1—
Single-bid contracts39%51%—34%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Comunitat Valenciana 12
  • Andalucía 11
  • Comunidad de Madrid 6
  • Castilla y León 2
  • Principado de Asturias 1

Procedures

  • Other procedure 29
  • Direct award 22
  • not stated 20
  • Restricted procedure 9
  • Simplified procedure 4
  • Open procedure 3

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Fasteners: screws, bolts and nuts

Questions and answers

How many fasteners tenders were published in Spain in June 2026?
87 (by 26 buyers); for comparison, May 2026: 70, June 2025: 72.
Who won the most fasteners tenders in Spain in June 2026?
By number of contracts: METALCO S.A. (5), SUMICAT S.L. (4), Wurth España.sa (4), Wurth España, S.A. (4) and AMIDATA, S.A.U. (3); 48 companies won contracts in all.
Which buyers published the most fasteners tenders in June 2026?
Dirección General de Renfe Ingeniería y Mantenimiento Sociedad Mercantil Estatal, S.A. (30), Junta de Gobierno Local del Ayuntamiento de Alicante (11), Universitat de Girona (8), Ajuntament de Vandellòs i l'Hospitalet de l'Infant (5) and Gerencia de la Empresa Municipal Autobuses de Córdoba S.A. (AUCORSA) (5).
How competitive were fasteners tenders in Spain in June 2026?
On average 2.2 bids per contract (57 contracts with a known number of bids); 39% of contracts had a single bid.
What were the contracts worth in June 2026?
€1,226,891 (awarded value, 77 contracts); median about €490.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.