Drainage works tenders in Czechia — market report, August 2025

Drainage works tenders in Czechia in August 2025: 118 tenders published (-7% month on month, -10% year on year), estimated at €65,456,902 in total, and 111 contracts awarded (-13% month on month, -13% year on year), worth €12,320,409 (contract value). Buyers with the most tenders: Správa a údržba silnic Ústeckého kraje, příspěvková organizace (6), Brněnské komunikace a.s. (3) and Správa silnic Moravskoslezského kraje, příspěvková organizace (3); most contracts won: Chládek & Tintěra, a.s. (4), Mott MacDonald CZ, spol. s r.o. (3) and Eurovia CZ a.s. (3). On average 3.1 bids per contract; 14% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
118
Contracts awarded
111
Contract value contract
€12,320,409
Bids per contract
3.1
Tenders published per month
050100150Aug 24: 131Aug 24: 131Aug 24Sep 24: 135Sep 24: 135Sep 24Oct 24: 139Oct 24: 139Oct 24Nov 24: 148Nov 24: 148Nov 24Dec 24: 108Dec 24: 108Dec 24Jan 25: 60Jan 25: 60Jan 25Feb 25: 72Feb 25: 72Feb 25Mar 25: 98Mar 25: 98Mar 25Apr 25: 106Apr 25: 106Apr 25May 25: 110May 25: 110May 25Jun 25: 148Jun 25: 148Jun 25Jul 25: 127Jul 25: 127Jul 25Aug 25: 118Aug 25: 118118Aug 25
Contracts awarded per month
050100150200Aug 24: 127Aug 24: 127Aug 24Sep 24: 137Sep 24: 137Sep 24Oct 24: 131Oct 24: 131Oct 24Nov 24: 146Nov 24: 146Nov 24Dec 24: 116Dec 24: 116Dec 24Jan 25: 74Jan 25: 74Jan 25Feb 25: 64Feb 25: 64Feb 25Mar 25: 115Mar 25: 115Mar 25Apr 25: 129Apr 25: 129Apr 25May 25: 117May 25: 117May 25Jun 25: 180Jun 25: 180Jun 25Jul 25: 127Jul 25: 127Jul 25Aug 25: 111Aug 25: 111111Aug 25

The highlighted bar is August 2025. Hover a bar for its figure; the table below has every value.

FigureAugust 2025July 2025ChangeAugust 2024Change
Tenders published118127-7%131-10%
Estimated value€65,456,902€375,172+17,347%€1,497,611+4,271%
Buyers3345-27%58-43%
Contracts awarded111127-13%127-13%
Contract value (contract)€12,320,409€10,256,255+20%€3,670,755+236%
Winners7892-15%97-20%
Bids per contract3.15.3—3.7—
Single-bid contracts14%0%—0%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Hlavní město Praha 4
  • Kraj Vysočina 2
  • Liberecký kraj 1
  • Královéhradecký kraj 1
  • Pardubický kraj 1

Procedures

  • not stated 106
  • Open procedure 5
  • Other procedure 5
  • Simplified procedure 2

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Drainage works and culverts

Questions and answers

How many drainage works tenders were published in Czechia in August 2025?
118 (by 33 buyers); for comparison, July 2025: 127, August 2024: 131.
Who won the most drainage works tenders in Czechia in August 2025?
By number of contracts: Chládek & Tintěra, a.s. (4), Mott MacDonald CZ, spol. s r.o. (3), Eurovia CZ a.s. (3), POHAS s.r.o. (2) and Agumont, s.r.o. (2); 78 companies won contracts in all.
Which buyers published the most drainage works tenders in August 2025?
Správa a údržba silnic Ústeckého kraje, příspěvková organizace (6), Brněnské komunikace a.s. (3), Správa silnic Moravskoslezského kraje, příspěvková organizace (3), statutární město Plzeň (3) and Statutární město Ostrava (2).
How competitive were drainage works tenders in Czechia in August 2025?
On average 3.1 bids per contract (7 contracts with a known number of bids); 14% of contracts had a single bid.
What were the contracts worth in August 2025?
€12,320,409 (contract value, 111 contracts); median about €18,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.