Market report

Construction tenders in Switzerland — market report, July 2025

Construction tenders in Switzerland in July 2025: 575 tenders published (+5% month on month, +24% year on year), and 645 contracts awarded (+3% month on month, +374% year on year), worth €1,047,538,345 (awarded value). Buyers with the most tenders: Kantonales Hochbauamt Thurgau (22), HBD - Amt für Hochbauten (AHB) (16) and Hochbauamt Kanton Zürich, Baubereich C (12); most contracts won: Groupe Egli AG (6), Egli AG Zürich, Niederhasli (5) and Frutiger AG (4). On average 4.4 bids per contract; 9% of contracts had a single bid. Report made on 27 October 2026.

Tenders published
575
Contracts awarded
645
Contract value awarded
€1,047,538,345
Bids per contract
4.4
Tenders published per month
0200400600800Jul 24: 462Jul 24: 462Jul 24Aug 24: 382Aug 24: 382Aug 24Sep 24: 462Sep 24: 462Sep 24Oct 24: 604Oct 24: 604Oct 24Nov 24: 560Nov 24: 560Nov 24Dec 24: 476Dec 24: 476Dec 24Jan 25: 550Jan 25: 550Jan 25Feb 25: 655Feb 25: 655Feb 25Mar 25: 711Mar 25: 711Mar 25Apr 25: 633Apr 25: 633Apr 25May 25: 604May 25: 604May 25Jun 25: 550Jun 25: 550Jun 25Jul 25: 575Jul 25: 575575Jul 25
Contracts awarded per month
0200400600800Jul 24: 136Jul 24: 136Jul 24Aug 24: 138Aug 24: 138Aug 24Sep 24: 255Sep 24: 255Sep 24Oct 24: 284Oct 24: 284Oct 24Nov 24: 438Nov 24: 438Nov 24Dec 24: 413Dec 24: 413Dec 24Jan 25: 490Jan 25: 490Jan 25Feb 25: 538Feb 25: 538Feb 25Mar 25: 700Mar 25: 700Mar 25Apr 25: 668Apr 25: 668Apr 25May 25: 602May 25: 602May 25Jun 25: 629Jun 25: 629Jun 25Jul 25: 645Jul 25: 645645Jul 25

The highlighted bar is July 2025. Hover a bar for its figure; the table below has every value.

FigureJuly 2025June 2025ChangeJuly 2024Change
Tenders published575550+5%462+24%
Estimated value—————
Buyers270276-2%257+5%
Contracts awarded645629+3%136+374%
Contract value (awarded)€1,047,538,345€910,610,053+15%€375,882,933+179%
Winners546516+6%117+367%
Bids per contract4.44.5—4.3—
Single-bid contracts9%8%—9%—

Buyers with the most tenders

Companies with the most contracts

Where the tenders were

  • Zürich 38
  • Vaud 29
  • Bern / Berne 24
  • Aargau 20
  • Genève 15

Procedures

  • Open procedure 517
  • Direct award 34
  • Simplified procedure 16
  • Restricted procedure 7
  • not stated 1

Download the figures (CSV)

The report's aggregates: the figures, the comparisons and the top lists by name and count.

All reports: Building construction and materials

Questions and answers

How many construction tenders were published in Switzerland in July 2025?
575 (by 270 buyers); for comparison, June 2025: 550, July 2024: 462.
Who won the most construction tenders in Switzerland in July 2025?
By number of contracts: Groupe Egli AG (6), Egli AG Zürich, Niederhasli (5), Frutiger AG (4), Grichting & Valterio Electro SA (4) and KIBAG Bauleistungen AG (4); 546 companies won contracts in all.
Which buyers published the most construction tenders in July 2025?
Kantonales Hochbauamt Thurgau (22), HBD - Amt für Hochbauten (AHB) (16), Hochbauamt Kanton Zürich, Baubereich C (12), Ville de Morges, urbanisme, constructions et espace public (12) and Burgergemeinde Bern (12).
How competitive were construction tenders in Switzerland in July 2025?
On average 4.4 bids per contract (608 contracts with a known number of bids); 9% of contracts had a single bid.
What were the contracts worth in July 2025?
€1,047,538,345 (awarded value, 645 contracts); median about €610,000.

How the report is made

Tenders published: the tenders of the sector or topic whose first notice is dated in the month (a tender counts in its sector and in up to three topics). Contracts awarded: the awards dated in the month, whenever their tender was published. Values in EUR, by value kind (never added together); medians are approximate (±3 %). Comparisons: with the reports of the previous month and of the same month a year earlier, each made the same way. The report was made on 27 October 2026 from the data of that day and is not changed afterwards; sources publish late, so later data for the month are not in it.